I'm working on a project that requires a consistent 6" h x 12" w x 52" long PC block. I've built the molds and have filled one to the top on the first pour and will backfill the shrinkage in a day or two. (photos attached)
My question is whether or not filling a 6" mold on the first pour is the best way or whether I should only fill it half way on the first pour.
For background, my mix is 1# paper, 1# portland, 1# sand, .05 # Borax. I live near Cincinnati and our summers are generally hot and humid.
Thanks
Dan
__._,_.___